Cardington-Liberty 69 kV IV
PJM queue ID AI2-082 Terminal status
| Queue ID | AI2-082 |
|---|---|
| Project name | Cardington-Liberty 69 kV IV |
| Status (as published) | Withdrawn |
| Substation | Cardington-Liberty IV |
| Point of interconnection | Cardington-Liberty 69 kV IV |
| County | Morrow |
| State | OH |
| Voltage | 69 kV |
| Capacity | 34.7 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 0 |
| Mw Capacity | 34.7 |
| Mfo | 101 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.