Substation Scout

Beatty - Biers Run 345 kV

PJM queue ID AI2-028 Terminal status

Queue IDAI2-028
Project nameBeatty - Biers Run 345 kV
Status (as published)Withdrawn
SubstationBeatty - Biers Run
Point of interconnectionBeatty - Biers Run 345 kV
CountyUnion
StateOH
Voltage345 kV
Capacity96 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-20
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy160
Mw Capacity96
Mfo160

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.