Substation Scout

Racine - Ravenswood 69kV

PJM queue ID AI2-024 Terminal status

Queue IDAI2-024
Project nameRacine - Ravenswood 69kV
Status (as published)Withdrawn
SubstationRacine - Ravenswood
Point of interconnectionRacine - Ravenswood 69kV
CountyMeigs
StateOH
Voltage69 kV
Capacity36 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity36
Mfo60

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.