Danieltown – Brunswick 115 kV

PJM queue ID AI2-004 Terminal status

Queue IDAI2-004
Project nameDanieltown – Brunswick 115 kV
Status (as published)Withdrawn
SubstationDanieltown – Brunswick
Point of interconnectionDanieltown – Brunswick 115 kV
CountyBrunswick
StateVA
Voltage115 kV
Capacity71.8 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2026-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity71.8
Mfo80

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.