Substation Scout

Remington 115 kV

PJM queue ID AI2-001 Terminal status

Queue IDAI2-001
Project nameRemington 115 kV
Status (as published)Withdrawn
SubstationRemington
Point of interconnectionRemington 115 kV
CountyCaroline
StateVA
Voltage115 kV
Capacity150 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-05-26
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity150
Mfo150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.