Philipsburg 115 kV V

PJM queue ID AI1-215 Terminal status

Queue IDAI1-215
Project namePhilipsburg 115 kV V
Status (as published)Withdrawn
SubstationPhilipsburg V
Point of interconnectionPhilipsburg 115 kV V
CountyCentre
StatePA
Voltage115 kV
Capacity20 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo180

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.