Brokaw 345 kV

PJM queue ID AI1-206 Terminal status

Queue IDAI1-206
Project nameBrokaw 345 kV
Status (as published)Withdrawn
SubstationBrokaw
Point of interconnectionBrokaw 345 kV
CountyNot reported
StateIL
Voltage345 kV
Capacity300 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy300
Mw Capacity300
Mfo300
Withdrawn Date11/22/2022