Substation Scout

Endless Caverns - Timberville 115 kV

PJM queue ID AI1-108 Terminal status

Queue IDAI1-108
Project nameEndless Caverns - Timberville 115 kV
Status (as published)Withdrawn
SubstationEndless Caverns - Timberville
Point of interconnectionEndless Caverns - Timberville 115 kV
CountyRockingham
StateVA
Voltage115 kV
Capacity33.1 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2026-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy38.5
Mw Capacity33.1
Mfo38.5
Withdrawn Date4/14/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.