Substation Scout

Laurel 25 kV

PJM queue ID AI1-082 Terminal status

Queue IDAI1-082
Project nameLaurel 25 kV
Status (as published)Withdrawn
SubstationLaurel
Point of interconnectionLaurel 25 kV
CountyWestmoreland
StatePA
Voltage25 kV
Capacity9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15
Mw Capacity9
Mfo15

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.