Substation Scout

New Castle 69 kV

PJM queue ID AH2-410 Terminal status

Queue IDAH2-410
Project nameNew Castle 69 kV
Status (as published)Withdrawn
SubstationNew Castle
Point of interconnectionNew Castle 69 kV
CountyNot reported
StateKY
Voltage69 kV
Capacity12 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2025-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.