Substation Scout

Wythe – Mount Airy 138 kV

PJM queue ID AH2-382 Terminal status

Queue IDAH2-382
Project nameWythe – Mount Airy 138 kV
Status (as published)Withdrawn
SubstationWythe – Mount Airy
Point of interconnectionWythe – Mount Airy 138 kV
CountyWythe
StateVA
Voltage138 kV
Capacity75 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy75
Mw Capacity75
Mfo75

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.