Substation Scout

Monroe 138kV

PJM queue ID AH2-378A Terminal status

Queue IDAH2-378A
Project nameMonroe 138kV
Status (as published)Withdrawn
SubstationMonroe
Point of interconnectionMonroe 138kV
CountyGloucester
StateNJ
Voltage138 kV
Capacity200 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity200
Mfo200

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.