Church - Oil City 138 kV III

PJM queue ID AH2-370 Terminal status

Queue IDAH2-370
Project nameChurch - Oil City 138 kV III
Status (as published)Withdrawn
SubstationChurch - Oil City III
Point of interconnectionChurch - Oil City 138 kV III
CountyCaroline
StateMD
Voltage138 kV
Capacity17.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-11-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy0
Mw Capacity17.816
Mfo112