Substation Scout

Emlenton - Clark Summit 34.5 kV

PJM queue ID AH2-355 Terminal status

Queue IDAH2-355
Project nameEmlenton - Clark Summit 34.5 kV
Status (as published)Withdrawn
SubstationEmlenton - Clark Summit
Point of interconnectionEmlenton - Clark Summit 34.5 kV
CountyVenango
StatePA
Voltage34.5 kV
Capacity5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy7.5
Mw Capacity5
Mfo7.5
Withdrawn Date9/7/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.