Substation Scout

Hurley 69 kV

PJM queue ID AH2-277 Terminal status

Queue IDAH2-277
Project nameHurley 69 kV
Status (as published)Withdrawn
SubstationHurley
Point of interconnectionHurley 69 kV
CountyBuchanan
StateVA
Voltage69 kV
Capacity42 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-03-10
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity42
Mfo60
Withdrawn Date10/20/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.