Central VA- Chase City 115kV

PJM queue ID AH2-271 Terminal status

Queue IDAH2-271
Project nameCentral VA- Chase City 115kV
Status (as published)Withdrawn
SubstationCentral VA- Chase City
Point of interconnectionCentral VA- Chase City 115kV
CountyMecklenburg
StateVA
Voltage115 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity90
Mfo150
Withdrawn Date1/15/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.