Swickley - Ambridge 23 kV

PJM queue ID AH2-245 Terminal status

Queue IDAH2-245
Project nameSwickley - Ambridge 23 kV
Status (as published)Withdrawn
SubstationSwickley - Ambridge
Point of interconnectionSwickley - Ambridge 23 kV
CountyAllegheny
StatePA
Voltage23 kV
Capacity25 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2023-09-29
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy25
Mw Capacity25
Mfo25