Crown - New Lebanon 69 kV

PJM queue ID AH2-242 Terminal status

Queue IDAH2-242
Project nameCrown - New Lebanon 69 kV
Status (as published)Withdrawn
SubstationCrown - New Lebanon
Point of interconnectionCrown - New Lebanon 69 kV
CountyMontgomery
StateOH
Voltage69 kV
Capacity40.5 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2027-03-08
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy45
Mw Capacity40.5
Mfo45

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.