Olive - Reynolds 345 kV

PJM queue ID AH2-233 Terminal status

Queue IDAH2-233
Project nameOlive - Reynolds 345 kV
Status (as published)Withdrawn
SubstationOlive - Reynolds
Point of interconnectionOlive - Reynolds 345 kV
CountyPulaski
StateIN
Voltage345 kV
Capacity100 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity100
Mfo100