Substation Scout

Not reported

PJM queue ID AH2-232 Terminal status

Queue IDAH2-232
Project nameNot reported
Status (as published)Withdrawn
SubstationNot reported
Point of interconnectionNot reported
CountyRockingham
StateVA
VoltageNot reported
Capacity25 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy25
Mw Capacity25
Mfo25
Withdrawn Date4/15/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.