Substation Scout

Trexlertown 12 kV

PJM queue ID AH2-178 Terminal status

Queue IDAH2-178
Project nameTrexlertown 12 kV
Status (as published)Withdrawn
SubstationTrexlertown
Point of interconnectionTrexlertown 12 kV
CountyNot reported
StateNot reported
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2024-06-21
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0
Mfo2
Withdrawn Date2/20/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.