Potter-Harlan 69 kV

PJM queue ID AH2-108 Terminal status

Queue IDAH2-108
Project namePotter-Harlan 69 kV
Status (as published)Withdrawn
SubstationPotter-Harlan
Point of interconnectionPotter-Harlan 69 kV
CountyLawrence
StatePA
Voltage69 kV
Capacity21 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy35
Mw Capacity21
Mfo95
Withdrawn Date3/18/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.