Jefferson 12.5 kV

PJM queue ID AH2-066 Terminal status

Queue IDAH2-066
Project nameJefferson 12.5 kV
Status (as published)Withdrawn
SubstationJefferson
Point of interconnectionJefferson 12.5 kV
CountyJefferson
StatePA
Voltage12.5 kV
Capacity3.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity3.3
Mfo5
Withdrawn Date4/28/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.