Edgewood 12.47 kV I

PJM queue ID AH2-054 Terminal status

Queue IDAH2-054
Project nameEdgewood 12.47 kV I
Status (as published)Withdrawn
SubstationEdgewood I
Point of interconnectionEdgewood 12.47 kV I
CountyWicomico
StateMD
Voltage12.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.98
Mw Capacity0
Mfo1.98

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.