Tasley 69kV

PJM queue ID AH2-050 Terminal status

Queue IDAH2-050
Project nameTasley 69kV
Status (as published)Withdrawn
SubstationTasley
Point of interconnectionTasley 69kV
CountyAccomack
StateVA
Voltage69 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2025-06-02
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.