Substation Scout

William - Blackwater 69 kV

PJM queue ID AH2-040 Terminal status

Queue IDAH2-040
Project nameWilliam - Blackwater 69 kV
Status (as published)Withdrawn
SubstationWilliam - Blackwater
Point of interconnectionWilliam - Blackwater 69 kV
CountyTucker
StateWV
Voltage69 kV
Capacity5.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy11.5
Mw Capacity5.7615
Mfo11.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.