Summer Shade - Barren County 161 kV
PJM queue ID AH2-021 Terminal status
| Queue ID | AH2-021 |
|---|---|
| Project name | Summer Shade - Barren County 161 kV |
| Status (as published) | Withdrawn |
| Substation | Summer Shade - Barren County |
| Point of interconnection | Summer Shade - Barren County 161 kV |
| County | Barren |
| State | KY |
| Voltage | 161 kV |
| Capacity | 105 MW |
| Resource (as published) | Solar; Storage |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2026-11-13 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 150 |
| Mw Capacity | 105 |
| Mfo | 150 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.