Substation Scout

Perth – Crystal Hill 115 kV

PJM queue ID AH2-004 Terminal status

Queue IDAH2-004
Project namePerth – Crystal Hill 115 kV
Status (as published)Withdrawn
SubstationPerth – Crystal Hill
Point of interconnectionPerth – Crystal Hill 115 kV
CountyHalifax
StateVA
Voltage115 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo20
Withdrawn Date12/1/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.