Substation Scout

Temple Hill - Roseville 69 kV

PJM queue ID AH2-002 Terminal status

Queue IDAH2-002
Project nameTemple Hill - Roseville 69 kV
Status (as published)Withdrawn
SubstationTemple Hill - Roseville
Point of interconnectionTemple Hill - Roseville 69 kV
CountyBarren
StateKY
Voltage69 kV
Capacity48 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity48
Mfo80

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.