Substation Scout

Not reported

PJM queue ID AH1-751 Terminal status

Queue IDAH1-751
Project nameNot reported
Status (as published)Withdrawn
SubstationNot reported
Point of interconnectionNot reported
CountyGreen
StateKY
VoltageNot reported
Capacity150 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-09-30
Source datasetcycle

Additional filed fields

DeveloperExie Solar, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StageRRI APPLICATION REVIEW
Mw Energy150.0
Mw Capacity150.0
Mfo300.0
Withdrawn Date5/2/2025
Withdrawn RemarksQueue Not Required
Last Updated5/5/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.