Substation Scout

Not reported

PJM queue ID AH1-743 Terminal status

Queue IDAH1-743
Project nameNot reported
Status (as published)Withdrawn
SubstationNot reported
Point of interconnectionNot reported
CountyShenandoah
StateVA
VoltageNot reported
Capacity255 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2029-04-30
Source datasetcycle

Additional filed fields

DeveloperLighthouse Storage, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StageRRI APPLICATION REVIEW
Mw Energy333.78
Mw Capacity255.0
Mfo333.78
Withdrawn Date5/2/2025
Withdrawn RemarksQueue Not Required
Last Updated5/5/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.