Delaware-Royerton 138 kV

PJM queue ID AH1-742 Terminal status

Queue IDAH1-742
Project nameDelaware-Royerton 138 kV
Status (as published)Withdrawn
SubstationDelaware-Royerton
Point of interconnectionDelaware-Royerton 138 kV
CountyDelaware
StateIN
Voltage138 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-10-30
Source datasetcycle

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperRoyerton Solar, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC2
StageRRI APPLICATION REVIEW
Mw Energy0.0
Mw Capacity20.0
Mfo140.0
Withdrawn Date5/2/2025
Withdrawn RemarksQueue Not Required
Last Updated5/5/2025