Saegers 230 kV
PJM queue ID AH1-707 Terminal status
| Queue ID | AH1-707 |
|---|---|
| Project name | Saegers 230 kV |
| Status (as published) | Withdrawn |
| Substation | Saegers |
| Point of interconnection | Saegers 230 kV |
| County | Lycoming |
| State | PA |
| Voltage | 230 kV |
| Capacity | 30 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | cycle |
Additional filed fields
| Developer | HAMILTON PATRIOT LLC |
|---|---|
| Transmission Owner | PPL |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Decision Point 1 |
| Mw Energy | 0.0 |
| Mw Capacity | 30.0 |
| Mfo | 907.0 |
| Submitted Date | 4/7/2025 |
| Withdrawn Date | 12/1/2025 |
| Withdrawn Remarks | CIW |
| Last Updated | 11/18/2025 |