Substation Scout

Not reported

PJM queue ID AH1-675 Terminal status

Queue IDAH1-675
Project nameNot reported
Status (as published)Withdrawn
SubstationNot reported
Point of interconnectionNot reported
CountyColumbia
StatePA
VoltageNot reported
Capacity2,070 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2030-06-30
Source datasetcycle

Additional filed fields

DeveloperInvitium Energy, LLC
Transmission OwnerPPL
Project TypeGeneration Interconnection
CycleTC2
StageRRI APPLICATION REVIEW
Mw Energy2175.0
Mw Capacity2070.0
Mfo2175.0
Withdrawn Date4/23/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated5/5/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.