Philipsburg-Shawville 34.5 kV

PJM queue ID AH1-667 Terminal status

Queue IDAH1-667
Project namePhilipsburg-Shawville 34.5 kV
Status (as published)Withdrawn
SubstationPhilipsburg-Shawville
Point of interconnectionPhilipsburg-Shawville 34.5 kV
CountyClearfield
StatePA
Voltage34.5 kV
Capacity10.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-03-01
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 10.8 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperCL-Shiloh LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy18.0
Mw Capacity10.8
Mfo18.0
Submitted Date2/29/2020
Withdrawn Date9/30/2026
Withdrawn RemarksCMN
Last Updated12/18/2025