Substation Scout

Cowen 138kV

PJM queue ID AH1-625 Terminal status

Queue IDAH1-625
Project nameCowen 138kV
Status (as published)Withdrawn
SubstationCowen
Point of interconnectionCowen 138kV
CountyWebster
StateWV
Voltage138 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy250
Mw Capacity150
Mfo250
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.