Messenger Brothers Solar II

PJM queue ID AH1-591 Terminal status

Queue IDAH1-591
Project nameMessenger Brothers Solar II
Status (as published)Withdrawn
SubstationCherry Ridge
Point of interconnectionCherry Ridge 66kV
CountyGrant
StateWV
Voltage66 kV
Capacity30 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-16
Source datasetcycle

Additional filed fields

DeveloperRWE Solar Development, LLC
Transmission OwnerAPS
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy50.0
Mw Capacity30.0
Mfo100.0
Submitted Date9/10/2021
Withdrawn Date7/8/2025
Withdrawn RemarksCustomer Initiated Withdrawal