Messenger Brothers Solar II
PJM queue ID AH1-591 Terminal status
| Queue ID | AH1-591 |
|---|---|
| Project name | Messenger Brothers Solar II |
| Status (as published) | Withdrawn |
| Substation | Cherry Ridge |
| Point of interconnection | Cherry Ridge 66kV |
| County | Grant |
| State | WV |
| Voltage | 66 kV |
| Capacity | 30 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2024-12-16 |
| Source dataset | cycle |
Additional filed fields
| Developer | RWE Solar Development, LLC |
|---|---|
| Transmission Owner | APS |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | PHASE 1 |
| Mw Energy | 50.0 |
| Mw Capacity | 30.0 |
| Mfo | 100.0 |
| Submitted Date | 9/10/2021 |
| Withdrawn Date | 7/8/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |
| Last Updated | 10/31/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.