Armstrong Battery Storage
PJM queue ID AH1-566 Terminal status
| Queue ID | AH1-566 |
|---|---|
| Project name | Armstrong Battery Storage |
| Status (as published) | Withdrawn |
| Substation | South Bend |
| Point of interconnection | South Bend 500kV |
| County | Armstrong |
| State | PA |
| Voltage | 500 kV |
| Capacity | 250 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2025-06-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Armstrong Power, LLC |
|---|---|
| Transmission Owner | APS |
| Project Type | Generation Interconnection |
| Cycle | TC2 |
| Stage | PHASE 1 |
| Mw Energy | 250.0 |
| Mw Capacity | 250.0 |
| Mfo | 1038.1 |
| Submitted Date | 9/10/2021 |
| Withdrawn Date | 6/30/2025 |
| Withdrawn Remarks | Customer Initiated Withdrawal |
| Last Updated | 10/31/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.