Substation Scout

Rockford II 138 kV

PJM queue ID AH1-564 Terminal status

Queue IDAH1-564
Project nameRockford II 138 kV
Status (as published)Withdrawn
SubstationRockford II
Point of interconnectionRockford II 138 kV
CountyWinnebago
StateIL
Voltage138 kV
Capacity150 MW
Resource (as published)Natural Gas,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2029-06-01
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 150 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperRockford Generation, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy150.0
Mw Capacity150.0
Mfo330.0
Submitted Date9/10/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated6/2/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.