Substation Scout

Bremo - Buckingham 230 kV

PJM queue ID AH1-546 Terminal status

Queue IDAH1-546
Project nameBremo - Buckingham 230 kV
Status (as published)Withdrawn
SubstationBremo - Buckingham
Point of interconnectionBremo - Buckingham 230 kV
CountyBuckingham
StateVA
Voltage230 kV
Capacity39 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-11-30
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 39 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperMountain Pine Arvonia LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy65.0
Mw Capacity39.0
Mfo65.0
Submitted Date9/10/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated6/29/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.