Substation Scout

Church-Oil City 138kV

PJM queue ID AH1-536 Terminal status

Queue IDAH1-536
Project nameChurch-Oil City 138kV
Status (as published)Withdrawn
SubstationChurch-Oil City
Point of interconnectionChurch-Oil City 138kV
CountyQueen Anne's
StateMD
Voltage138 kV
Capacity8.5 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2028-03-01
Source datasetcycle

Additional filed fields

DeveloperOld Line Energy, LLC
Transmission OwnerDPL
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 1
Mw Energy41.8
Mw Capacity8.5
Mfo41.8
Submitted Date9/10/2021
Withdrawn Date12/2/2025
Withdrawn RemarksCIW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.