Substation Scout

Greenwood Solar II

PJM queue ID AH1-533 Terminal status

Queue IDAH1-533
Project nameGreenwood Solar II
Status (as published)Withdrawn
SubstationSunbury-Juniata II
Point of interconnectionSunbury-Juniata II
CountyPerry
StatePA
VoltageNot reported
Capacity38.5 MW
Resource (as published)Solar,Storage,Hybrid
Resource categoryHybrid (normalised for filtering)
Target commercial operation2025-03-01
Source datasetcycle

Additional filed fields

DeveloperNorth Corners Energy, LLC
Transmission OwnerPPL
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy96.2
Mw Capacity38.5
Mfo185.2
Submitted Date9/10/2021
Withdrawn Date7/3/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025