Substation Scout

TBD 12 kV

PJM queue ID AH1-509 Terminal status

Queue IDAH1-509
Project nameTBD 12 kV
Status (as published)Withdrawn
SubstationTBD
Point of interconnectionTBD 12 kV
CountyNorthumberland
StatePA
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Withdrawn Date3/14/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.