Substation Scout

Grand View Solar I

PJM queue ID AH1-492 Terminal status

Queue IDAH1-492
Project nameGrand View Solar I
Status (as published)Withdrawn
SubstationBernville
Point of interconnectionBernville 13 kV
CountyBerks
StatePA
Voltage13 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-07-30
Source datasetcycle

Additional filed fields

DeveloperPD Solar 2 LLC
Transmission OwnerME
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy20.0
Mw Capacity12.0
Mfo20.0
Submitted Date9/11/2021
Withdrawn Date6/9/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025