Substation Scout

Maysville 34.5 kV 3

PJM queue ID AH1-488 Terminal status

Queue IDAH1-488
Project nameMaysville 34.5 kV 3
Status (as published)Withdrawn
SubstationMaysville 3
Point of interconnectionMaysville 34.5 kV 3
CountyMercer
StatePA
Voltage34.5 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-07-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo20
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.