Substation Scout

Madison - Tanners Creek 138 kV

PJM queue ID AH1-484 Terminal status

Queue IDAH1-484
Project nameMadison - Tanners Creek 138 kV
Status (as published)Withdrawn
SubstationMadison - Tanners Creek
Point of interconnectionMadison - Tanners Creek 138 kV
CountyHenry
StateIN
Voltage138 kV
Capacity115 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-09-24
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy115
Mw Capacity115
Mfo267.5
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.