Substation Scout

Reynolds - Meadow Lake #1 345 kV

PJM queue ID AH1-481 Terminal status

Queue IDAH1-481
Project nameReynolds - Meadow Lake #1 345 kV
Status (as published)Withdrawn
SubstationReynolds - Meadow Lake #1
Point of interconnectionReynolds - Meadow Lake #1 345 kV
CountyWhite
StateIN
Voltage345 kV
Capacity84 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-09-25
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy84
Mw Capacity84
Mfo196
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.