Substation Scout

Owingsville - Preston 69 kV

PJM queue ID AH1-463 Terminal status

Queue IDAH1-463
Project nameOwingsville - Preston 69 kV
Status (as published)Withdrawn
SubstationOwingsville - Preston
Point of interconnectionOwingsville - Preston 69 kV
CountyBath
StateKY
Voltage69 kV
Capacity39 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetcycle

Additional filed fields

DeveloperPreston Solar, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 1
Mw Energy65.0
Mw Capacity39.0
Mfo65.0
Submitted Date9/10/2021
Withdrawn Date4/22/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated10/31/2025