Substation Scout

Julius Solar

PJM queue ID AH1-460 Terminal status

Queue IDAH1-460
Project nameJulius Solar
Status (as published)Withdrawn
SubstationHooversville - Scalp Level
Point of interconnectionHooversville - Scalp Level 115 kV
CountySomerset
StatePA
Voltage115 kV
Capacity39.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 39.6 Active → Withdrawn

Full change log →

Additional filed fields

DeveloperJulius Energy, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC2
StageDecision Point 2
Mw Energy66.0
Mw Capacity39.6
Mfo66.0
Submitted Date9/10/2021
Withdrawn Date9/30/2026
Withdrawn RemarksCIW
Last Updated12/29/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.