Substation Scout

Hampshire - Ridgeley 138 kV 2

PJM queue ID AH1-459 Terminal status

Queue IDAH1-459
Project nameHampshire - Ridgeley 138 kV 2
Status (as published)Withdrawn
SubstationHampshire - Ridgeley 2
Point of interconnectionHampshire - Ridgeley 138 kV 2
CountyHampshire
StateWV
Voltage138 kV
Capacity50 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2024-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity50
Mfo150
Withdrawn Date12/18/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.